The complex LTCS and duplex bore spools fabrication included:

– 750 NB Piping heavy wall piping
– 100+ welded joints completed with minimal weld repairs
– TIG, FCAW, SAW and TIP-TIG welding techniques utilised
– Humidur coating applied
– Hot work insulation

Fabrication of the large pipe bridges and structures included:

– > 60 tonne Plus trestles and pipe bridges
– L0 testing and Z25 testing applied to all material
– 100+ Pipe supports
– Surveyed structure for easy install on site

The spools fabrication was complex, with weld procedure specifications required for duplex/carbon overlay welding and an acute focus on quality was maintained throughout to achieve the desired result.

The fabrication was completed over of 20,000+ man hours with Zero LTI’s.

CASE STUDIES

Chevron Gorgon BOG Flare Maintenance

The scope involved recoating the entire BOG Flare pipeline in the SA Modules. The larger diameter…

Nyrstar Zinc Works – Shutdown, Refractory and Associated Works

AGC was selected as Nyrstar’s refractory and scaffolding contractor for its 2014 and 2017 Major Turnarounds.…

Rio Tinto Alcan Yarwun – Maintenance Contract

AGC was commissioned to provide Yarwun with a range of integrated services including; refractory, mechanical and…