The complex LTCS and duplex bore spools fabrication included:

– 750 NB Piping heavy wall piping
– 100+ welded joints completed with minimal weld repairs
– TIG, FCAW, SAW and TIP-TIG welding techniques utilised
– Humidur coating applied
– Hot work insulation

Fabrication of the large pipe bridges and structures included:

– > 60 tonne Plus trestles and pipe bridges
– L0 testing and Z25 testing applied to all material
– 100+ Pipe supports
– Surveyed structure for easy install on site

The spools fabrication was complex, with weld procedure specifications required for duplex/carbon overlay welding and an acute focus on quality was maintained throughout to achieve the desired result.

The fabrication was completed over of 20,000+ man hours with Zero LTI’s.

CASE STUDIES

Turnaround Maintenance Project for LNG Upstream and Downstream

The Project The second of the planned turnaround maintenance programs for a key LNG operator in…

Wheatstone Loading Arm Remediation

The Product Loading Facility (PLF) Loading Arm Remediation Project was initiated to provide permanent solutions for…

Fabrication of complete Long Travel Bogie Assemblies

AusGroup were contracted by the client to fabricate, assemble and transport 4 ship loader long travel…