Fabrication Location – Kwinana workshop

  • Bay 1 Carbon Steel Fabrication
  • Bay 2 Stainless Steel Fabrication
  • In-House painting
  • Assembly in Bay 1

Client Site Location

These project works were destined for the client’s salt processing location at their Lake MacLeod (Site) in the Gascoyne region of Western Australia, approximately 900 km North of Perth. The Project Site is located within the SP1 stockpile area at Lake MacLeod’s out loading facility at Cape Cuvier.

A Client Win

AusGroup provided a one-stop-shop fabrication, assembly, PIF and installation solution for the client with all 3rd party inspections being complied with throughout the process.

An AusGroup Win

The client was extremely impressed with the timeline AusGroup achieved and our agility when we had to react to change.

CASE STUDIES

Yara Pilbara Ammonia Plant

Yara Pilbara’s ammonia plant underwent a major turnaround in July 2018. For this window, AGC executed…

Woodside Greater Western Flank – Subsea Pipe Spools

As part of the Greater Western Flank Project Phase 1, AGC was subcontracted by Fugro-TSM to…

Acciona Waste to Energy Modules

East Rockingham Waste to Energy Project (ERWtE) Boiler Hall Structural Offsite Pre-Assembly