Peak Manning:   60+
Pricing Model:   Norms Estimate
Project Metrics:

  • Original budget estimated hours per train: 26,647.74hrs
  • Train 3 Actual hours: 26,626.36hrs (21.38hrs saved)
  • Train 2 Actual hours: 21,877.52hrs (4,770.22hrs saved)
  • Train 1 Actual hours: 20,001.27hrs (6,646.47hrs saved)
  • Total hours saved: 11,438.07hrs

 

Continuous Improvement Initiatives

  • SIMOPS with other contractors was achieved by implementation of daily meetings, addressing all relevant planned activities and discussing opportunities for improvement where possible.
  • In the pre-planning phase, requesting the required data from other disciplines, such as weld maps & NDT reports to optimize resource scheduling and work front availability.

CASE STUDIES

Turnaround Maintenance Project for LNG Upstream and Downstream

The Project The second of the planned turnaround maintenance programs for a key LNG operator in…

CBH Ship Loader Refurbishment Contract

AGC was contracted to refurbish Ship Loaders 3 and 4 at Kwinana for CBH. The scope…

Fabrication of complete Long Travel Bogie Assemblies

AusGroup were contracted by the client to fabricate, assemble and transport 4 ship loader long travel…