Peak Manning:   60+
Pricing Model:   Norms Estimate
Project Metrics:

  • Original budget estimated hours per train: 26,647.74hrs
  • Train 3 Actual hours: 26,626.36hrs (21.38hrs saved)
  • Train 2 Actual hours: 21,877.52hrs (4,770.22hrs saved)
  • Train 1 Actual hours: 20,001.27hrs (6,646.47hrs saved)
  • Total hours saved: 11,438.07hrs

 

Continuous Improvement Initiatives

  • SIMOPS with other contractors was achieved by implementation of daily meetings, addressing all relevant planned activities and discussing opportunities for improvement where possible.
  • In the pre-planning phase, requesting the required data from other disciplines, such as weld maps & NDT reports to optimize resource scheduling and work front availability.

CASE STUDIES

Turnaround Maintenance Project for LNG Upstream and Downstream

The Project The second of the planned turnaround maintenance programs for a key LNG operator in…

Woodside LTCS Bore Spools and Pipes

Fabrication of low temperature carbon steel (LTCS) and duplex bore spools and large pipe bridges and…

INPEX-operated Ichthys LNG Project – Module Insulation

AGC was contracted for the supply, fabrication and installation of all Cryogenic, Acoustic and Hot Insulation…