Peak Manning:   60+
Pricing Model:   Norms Estimate
Project Metrics:

  • Original budget estimated hours per train: 26,647.74hrs
  • Train 3 Actual hours: 26,626.36hrs (21.38hrs saved)
  • Train 2 Actual hours: 21,877.52hrs (4,770.22hrs saved)
  • Train 1 Actual hours: 20,001.27hrs (6,646.47hrs saved)
  • Total hours saved: 11,438.07hrs

 

Continuous Improvement Initiatives

  • SIMOPS with other contractors was achieved by implementation of daily meetings, addressing all relevant planned activities and discussing opportunities for improvement where possible.
  • In the pre-planning phase, requesting the required data from other disciplines, such as weld maps & NDT reports to optimize resource scheduling and work front availability.

CASE STUDIES

Rio Tinto Cape Lambert Screenhouse Rebuild

AusGroup was commissioned for the supply, fabrication, surface treatment and assembly of structural steel, platework, handrails,…

CSBP Brownfield Maintenance and Support Services

AusGroup were awarded a contract brownfield maintenance and in 2020 to provide support services for the…

Chevron Substation Lighting Facilities Maintenance

Site wide replacement of light tubes for all substation lighting. Replacement of faulty light fittings, battery…