The Scope
With previous experience at Kwinana Waste to Energy Project, AusGroup was contracted to pre-assemble 8 x modules (cubes) Bag and Boiler House structures and Hoppers at AusGroup’s Kwinana Operations, which features a large laydown and assembly area >25,000m2, transportation to site and onsite installation. Overall breakdown of works included:
- Receiving and checking materials using Track Base
- Specialist fabrication and welding
- Pre-assembly of 8 x Modules
- Specialist fabric filters and insultation on the Hoppers
- Pre-assembly of structural steel into transportable modules (cubes, towers or panels)
- Transportation envelope planning from AusGroup Kwinana facility to the project location
- Transportation of all structures to site
Watch the video here.
CASE STUDIES
CSBP Ammonium Nitrate Expansion Project – Prilling Plant Upgrade
The contract included debottlenecking works to the existing prilling plant and was be undertaken at CSBP…
Chevron-operated Gorgon LNG Project – Scaffold & Associated Services
MAS Australasia secured a contract with CKJV on the Chevron-operated Gorgon Project for ongoing scaffolding and…
Sino Iron Project Power Plant – Thermal Insulation
The scope involved the application of thermal insulation and cladding to piping and equipment for the…