The scope of the overall project included the redesign and replacement of loading line pipework, pipe supports, process design, control valves and instrumentation for each of the four LNG loading arms A,B,C & Hybrid.

The Project includes:

  • Offsite engineering support provided from constructability & HAZID inputs along with workpack and detailed schedule development for all disciplines
  • The project design and installation sequence development
  • Removal of the existing and installation of the new DN600 & DN750 spools, valves, supports and ancillaries
  • Offsite spool and support fabrication
  • Onsite SMP, E&I, Access, PIF & Rope Access services
  • Approx. 10,000m of cables ran alongside the jetty using a team of Rope Access and E&I Technicians.

 

CASE STUDIES

Karara Early Works Contract

AGC was engaged to provide the structural, mechanical and piping installation works and procurement of piping,…

Wheatstone Turnaround Planning (TAR 501/502)

The Wheatstone Asset’s turnaround (TAR) maintenance project commenced with the extensive planning services provided by AusGroup…

Cloudbreak Iron Ore Mine Expansion

AGC and Kiewit partnered in a JV for the contract which included the addition of; a…