Project Metrics
Overall achieved norms of 20hrs per tonne erect and 10 hrs per tonne dismantle
The Project
AusGroup was engaged to provide scaffolding access services at the Wheatstone facility.
Continuous Improvement Initiatives
- AusGroup introduced the scaffolding norms from Gorgon to transition from a T&M Model to a Norms Execution model.
- Improved Norms by 20% utilizing ATPAC Modular Scaffold
- Detailed Norms built for Standard ATPAC Scaffold, ATPAC Modular Scaffold, Tube and Clip Scaffold and Engineered Scaffold for WHS.
- Introduced ExTag Scaffold App that produces Scaffolding Dashboards and Live Mapping
CASE STUDIES
Chevron Gorgon BOG Flare Maintenance
The scope involved recoating the entire BOG Flare pipeline in the SA Modules. The larger diameter…
Wheatstone Platform Fender Removal
During the installation of WHS Platform, the temporary fenders were left to be removed at a…
CSBP Brownfield Maintenance and Support Services
AusGroup were awarded a contract brownfield maintenance and in 2020 to provide support services for the…