AusGroup was subcontracted by Thyssenkrupp to fabriacte and assemble the components for the RC03 reclaimer the world’s largest on rail reclaimer ever made.
The Project
Reclaimer package consisted of 10 x major structural components.
- Substructure 240t module
- Cross Equalizer 42.5t
- Reeler platform 12.5t module
- Equipment platform 44t module
- Bucket wheel boom 170.5t module
- Pylon 5.7t
- Slew deck 113.5t module
- Counterweight boom 62t module
- Boom mast 27.2t module
- Pantograph 129t module
All items were fabricated at the AusGroup Kwinana Operations. AGC was also asked with assembling all modules to full extenet as allowed by transport. Some modules were in excess of 240t, 15m wide (the widest ever transported on Perth metro roads) and one module 69m long.
Watch the video here.
CASE STUDIES
Yara Pilbara Ammonia Plant
Yara Pilbara’s ammonia plant underwent a major turnaround in July 2018. For this window, AGC executed…
Southern Seawater Desalination Plant – Structural, Mechanical & Installation
The scope of work for AGC covered the structural, mechanical and installation work associated with the…
Dampier Salt Truss, Lifting Bean and SS Chute Fabrication (CV02)
The Project Dampier Salt engaged AusGroup to fabricate, assemble and deliver various replacement components of the…